CS-100L Commercial Storage Quick Start
This guide covers site installation, pre-connection checks and first power-up for the CS-100L commercial cabinet.

Before installation
| Item | Requirement |
|---|---|
| Foundation | Level, load capacity ≥ 2,000kg, service clearance |
| Environment | -20°C–50°C, ventilated, no corrosive gas |
| Grid | Confirm transformer capacity, metering and protection settings |
Installation steps
- Fix the cabinet and connect earth; resistance ≤4Ω.
- Connect battery, PCS and grid cables by label.
- Verify E-stop, fire and thermal interlocks.
- Complete insulation, communication and protection tests.
First power-up
- Check battery SOC and cell delta.
- Verify EMS communication, meter direction and alarms.
- Record and file the pre-connection acceptance.