Storage Project Acceptance Template

Documentation/

Storage Project Acceptance Template

项目验收所需的检查项与记录表模板。

Storage Project Acceptance Template
Storage Project Acceptance Template · Demo document

Scope

This document is for EVX installation, commissioning, service and acceptance teams. Confirm the model, site conditions and local grid requirements before starting.

Procedure

  1. Check the nameplate, documents and site conditions.
  2. Complete wiring and verify earthing and protection.
  3. Power up and check communications, alarms and operating status.
  4. Record the checks and complete handover or acceptance.

Checklist

ItemRequirement
EnvironmentVentilated, dry, within datasheet range
Earthing≤4Ω, secure connection
CommunicationsEMS, meter and platform data healthy
SafetyFire, E-stop and alarm interlocks active

Notes

  • Isolate and tag the equipment before work.
  • High-voltage work must be performed by qualified personnel.
  • Refer to the current datasheet for exact values.