EVX Project Delivery Pack

Documentation/

EVX Project Delivery Pack

项目交付、并网与验收所需的资料清单。

EVX Project Delivery Pack
EVX Project Delivery Pack · Demo document

Scope

This document is for EVX installation, commissioning, service and acceptance teams. Confirm the model, site conditions and local grid requirements before starting.

Procedure

  1. Check the nameplate, documents and site conditions.
  2. Complete wiring and verify earthing and protection.
  3. Power up and check communications, alarms and operating status.
  4. Record the checks and complete handover or acceptance.

Checklist

ItemRequirement
EnvironmentVentilated, dry, within datasheet range
Earthing≤4Ω, secure connection
CommunicationsEMS, meter and platform data healthy
SafetyFire, E-stop and alarm interlocks active

Notes

  • Isolate and tag the equipment before work.
  • High-voltage work must be performed by qualified personnel.
  • Refer to the current datasheet for exact values.